Construction updates for the Grand Avenue Bridge will be provided by Grand Avenue Bridge Public Information throughout the duration of the project, which spans a long time period and impacts many CMC staff and students. The goal is to keep Roaring Fork Valley locals and visitors informed about coming detours, traffic information, and project progress. A summary of the first week’s activity is below. Going forward, the college plans to post construction updates on the Basecamp portal so they are easilyl accessible to staff and students whom construction updates significantly affect.
Construction Activity for the week of Jan. 4 – Jan. 10, 2016.
Location: West of the intersection of Colorado Avenue and 7th St., the contractor will be working on construction of a causeway.
- Completion of the railroad crossing west of the intersection of Colorado Avenue and 7th St.
- Trucks will be dumping and hauling causeway materials in this area.
- Anticipate 8 trucks per hour or roughly 75 trucks per day during construction hours M-F 7 a.m.-5 p.m. No construction activity during the weekends.
Traffic Impacts for the week of Jan. 4 – Jan. 10, 2016.
- Expect periodic 7th St. closures west of the intersection of Colorado Avenue and 7th St. to allow for trucks to access the causeway.
- On Tuesday, Jan. 5th, the north lane will be closed at the railroad crossing to set a barrier.
- Traffic control will be managing periodic stops.
Pedestrian Access
- The sidewalk along the north side of 7th St. will be closed between Colorado Avenue and Cooper Avenue.
- Access to the pedestrian bridge will remain open.
Construction Activities Occurring (January 2016)
Construction of a causeway, the south pier caisson and utility work.
Causeway: The contractor is building a causeway (temporary rock road) along the Colorado River bank to use as a working platform. A causeway is needed to create closer access to the bridge. This causeway is roughly 500 ft. long and 50-75 ft. wide. The causeway will be made out of rock and will be removed when the project is complete. Cranes, drills, and trucks will be staged on the causeway.
Utility work: The contractor is installing a storm drain line and a permanent waterline. Deep utility work begins along the north lane of 7th St between Colorado Avenue and Cooper Avenue.
Caisson construction: The contractor will begin building a caisson for construction of the south pier. A caisson is large water tight retaining structure used to work on the foundation of the bridge pier. Construction activities such as shoring and screw micro-piling will occur to reinforce the foundation of the piers.
Upcoming Construction Activity
- Beginning the week of Jan. 11 – Jan. 15, 2016 the contractor will remove the public restrooms and existing walls under existing GAB on north side of 7th St.
- A one-lane closure from Colorado Avenue to Cooper Avenue will be ongoing for several months, as the contractor is constructing the causeway and installing deep utilities.
Construction Hours
7:00 a.m. – 5:00 p.m. M-F
PROJECT HOTLINE
Call or Text: 970-618-9897